January 3, 1901
Brady & Gay to Bihler--Our clients state that the beinning of the first
channel changes was made at about Station 60. They claim that the
engineer took his elevations but faioled to discover that the old
channel was one foot and a half deeper on the opposite bank,
consequently the new channel was not deep enough and was cut in at right
angles without any allowance being made for turning the mouth of the
channel up against the stream, and the water would not go in the new
channel and the water turned all of its velocity against the dam which
had been put in. This dam at that time consisted of coarse gravel and
rocks and of course was destroyed. Then the engineer resorted to sand
bages, hay etc., for the purpose of making a dam.
The crew of men, as stated in the account on page 2 and the following
pages, were kept constantly in doing the force account work. The men
were put into the creek in deppt water. The creek, whcihw as then
practically a river, had a velocity of as much as forty miles per hour.
Some of the men worked deepinging part of the cannnel and others were
put at the entracne to change from the square system to the radius
system. It was very difficult to get men to work in the cold water. They
had to be supplied with rubber boots. Each pair of boots would not least
longer than a week. All kinds of inducements had to be offered to the
men to get them to do the work under the trying circumstnaces. A large
bolder [sic] was blasted which was considreded below grade. Trees were
washed down. These trees with the other drift would form dams that
threatened the whole construction.
At Stations 66 to 71 the present embankment was placed in the channel
of the creek as it then existed, which was practically a river. The
current was too strong for the embankement, therefore a temporary
channel was mdeae on the right hand side to hadne the immense volume of
water that roared through the canyon. This temporary channel was dug
through swampy ground full of roots and stumps, and as the temporary
channel was four feet higher than the old channel a sheer dam had to be
made whcih consisted of logs, brush and gravel. This sheer dam was made
with much difficulty, the work was dangerous and tedious. Many times the
water broke through the sturcture and washed it overboard. The stream of
water was then practically a catarat. After very much hard work this
sheer dam was completed.
At the entrance of channel No. 2, beginning about Station 66, the
embankment was no able to hold the stream from overflowing. A force of
men was directed to enlarge the channel by embankemnt on the berm. This
embankment practically became a levy and a great amont of work was spent
in raising it and making it higher.
Men had to be kept at work to keep the channel deep enough at the
intersection of Susie [Soos] and Kenkins Creek. Hugh [sic] windfalls had
to be removed. Old trees measuring eight feet in diameter were in these
windfalls. Blasting had to be resorrted to and this method had to be
used all the way up Jenkins Creek to apoint about fifty feet outside of
the right of way line. Much gravel deposited at the outlet of Susie
Creek. Excavations had to be continued. The force gang could scarecely
remove this gravel as fast as it formed. Some right of way work was done
to extend the cahannel further down the stream. The stream had to be
cleared of the windfalls. Dynamite had to be used under water. Stumps
and bolders [sic] for a long distance were thus removed time and tiem
again during the winter months.
This explanation should give you a clear conception of the work that
our clients had to do.
Note: Bihler forwarded above to Henry & Bennet on January 24, 1901.
March 25, 1901
Henry & Bennett to McHenry--[Holman & McGee have brought suit against
Henry & Bennett and Henry is seeking information for his attorney to
respond with] It is all a scheme of the lawyers and, with the help we
hope to get from your Company, I have no fears of the result. What I
wish is to knock the underpinning completely from under them. Our
contract with these subs is made upong the same blanks as our own with
your company. ... Our books show McGee & Holman in debt to us between
three and four thousand dollars.
March 29, 1901
Bihler to Henry & Bennett--I have talked this over with Mr. Kyle wo was
Asst. Engineer on this work, and he informs me that the following is the
true cause of their troubel from water in the differecnt channel changes
on this work: In makin excavation for changing this channel, the took
out a narrow ditch, and not down to grade. Tey then filled in the
railway embankment, expecting by doing this to force all of the water
down throgh their new channels, would could cause the same to wash out
the balance of their change of channel, and by thus doing, save them
considerable work and expnse. When they had made this small channel to
allow some of the water to go down as a start and had filled in their
railway embankment, closing up the original channel, the water did not
act as they had intended in cutting out the channel to the proper size,
but instead flooded them out and cut around their embankment, and they
were obliged to excvatate this channel change to the proper depth, as
the current would not was it out itself, and that the whole cause of
their having to excavate below waer, was on account of their own
carelessness, and because their plans would not work.
This was not a plan of the Railway Company's in any nature whatever,
as the contractors were simply required to make a channel change of a
certain size, and were allowed to go at it and do it in whatever way
they pleased, and they endevored to work a scheme to make considerable
money at this point, and their scheme failed them in that the wash of
the creek was not enough to excavate out the cahnnel, and they were
oblied to go into the water and do it by hand.
RESIDENCY, DOUGLAS KYLE, PALMER, WASH., 1899-1900
Fifty-one men in party circa November 1899, built bunkhouse at
Palmer--45 feet long, 16 feet, five inches wide, 15 feet high at one
side and 13 on the other.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., August 9, 1899
I wish you would have Wm. York send the tent fly he took when leaving
here I was going to use them this morning and was one short and one of
the boys said he rolled it up and took it with him when they left here
and give him my regards.
Note: in handwriting--DK Don't suppose you will need one now. How about
it? RG 8/22/99
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., n.d., circa August 1899
Have a contractor on Mile No. 2 and will start him clearing from 104
back will it be all right to grade back to Sta. 73 now.
Note: In handwriting--From 52 plus to 73 and 100 - 104 was that right RG
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 2, 1899
Have line cross-sectioned form Station 0 to Station 80 and from Station
116 to Station 176 and drain pipes stkaed out to Station 175 and all
right of way stakes in from 0 to 242 and bridge staked out and passing
track center line in.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 4, 1899
I cross-sectioned Allen's cut over and the one from Station 116 to 105
14 foot base on the cut side of curve do you want the cut between 118
and 122 cross-sectioned the same it would leave very little dirt in cut
and could not use steam shovel very well.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 4, 1899
I do not think Larence will be able to do this work here as he is
drinking to [sic] much I was at the bridge this morning and the men were
doing nothing for want of insturctions what to do I told the carpenter
to go a head and unload the material and do what he could and I would
help him out.
Note: In handwriting--"Wired Bihler to send another man to take his
place. 9/5/99"
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 7, 1899
Have line corss-sectioned from Station 0 to Sation 85 and from Station
108 to Station 179 and have change of line made from Sation 174 plus to
151 plus and from Staiton 190 plus to 209 plus and RW staked out on
Green River Northern and passing track and located one end of siding and
bridge staked out.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 6, 1899
The reason the cars are not unloaded the contractors are short of men
and soon as they change them from one place to another they quit. We
will keep the cars unloaded if we can and will have to use the bridge
men tomorrow to unload [two] cars of steel as we can not get Allen or
Morrison either as they have no men and I have told Olof [Olaf
Fjoertoft] to check Larrines times on Henry & Bennett's material when
unloading.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 9, 1899
I was up to see what we could find for spur on Green River North. I
think we can up in spur just above the old house starting from the tang
there and can get in about 700 feet of track if necessary but will have
to cut a few small brush at this end and will need very little leveling
to get in track and we could start at the old house little this side of
the curve and get out on the same ground.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 14, 1899
We can get unloading spur at the wagon road can lay track in the road
after is good many stumps there and will like up cars of men and if the
upper place is the bst and can get there with wagons as there will be
good road along that [?].
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 16, 1899
Have line cross-sectioned from Sation 0 to 85 and from Sation 108 to
Station 176 and from Station 203 to Station 227 and all Ry. staked set
and on Green River & Northern and have passing track staked out and east
end of track and part of the pipes checked.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 21, 1899
Finished grading the spur to day. It was cleared Sunday and did no
grading until to day and I just done it roughly and we can get the steel
on it allright. I ask section men today if he had any word about laying
it.
I saw McFee and he said he would come up and have the material piled
in good shape and would keep the different lenghts to the [?]
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 21, 1899
There is 7 cars of steel on track at Palmer and we will not be able to
get them unloaded until tomorrow. McFee was up last night and hvae made
arrangemetns for men at Camp No. 3 to unlad all materailly that comes
and will get stell off as soon as possible.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., September 30, 1899
Have line cross-sectioned from Station 0 to Station 80 and from Station
111 to Station 180 and Station 203 to Station 226 plus 50 and siding and
have track cross-sectioned and bridge all staked out and checked.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., October 25, 1899
I recieved level from C.S. Bihler and have returned the old one to him
this A.M.
The adjusting screws of the cross hairs were worn so they would not
hold as they are all worn out and have the screws out of the plate shut
holds the four screws and have had it tied up with thread. Ever since I
have had it and the adjusting screws were worn out when I took the level
and ptached it up.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., October 28, 1899
The truss on Green River Northern Ry. over Green River is broken and we
will not be able to get to the mateiral up to the yard. What will we do
with matieral that comes for there. We have on car on track now for
there.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., n.d., circa October 1899
Four hundred feet of track laid on unloading spur.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., November 10, 1899
I wish you would have them send me another level out as this one is no
good. The glass is so poor that I cant use it when it is cloudy or damp.
I tryed [sic] to use it yesterday settign grades and could not even read
the target anywhere.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., December 28, 1899
I wired you to day to send me tent and cook stove. Jack Simpson came
this morning and he would not go to work with the out fit we have here
and I told him to go to work and we would get them. The stove is worn
out and no good and the tent is so rotten ti will not stand to be moved
and the widn is liable to tear it to pieces any time.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., n.d., circa December 1899
Allen is grading upper end of GR&N.
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., n.d., circa December 1899
The contracor is in need of more second class steel for track will it be
all right to let them have that in yard as we have [13] miles there.
George A. Kyle, Assistant Engineer, Auburn, Wash., to Douglas Kyle,
Resident Engineer, Palmer, Wash., Febuary 25, 1900
I send you herewith paychecks in favor of the followin named men, for
deilvery. (Douglas Kyle, Raymond Jeckman, Walter M. Anderson, Lee Van
Slyke, Jack Simpson).
Douglas Kyle, Resident Engineer, Palmer, Wash., to George A. Kyle,
Assistant Engineer, Auburn, Wash., April 25, 1900
Will you please send me grate for stoeve Monitor Jr. Range No. 22 and
six feet of fly screen?
LINE WORK, PALMER CUT-OFF, 1899-1900
McHenry to Bihler, June 29, 1899
Furnish notes junction points Palmer Cut-Off.
Note: in handwriting
Connect with main line Pac. Div. 1st Dist. at Station 11110+23 = Mile
210.620 from Pasco
Connect with Seattle Line at Station 475+23 = Mile 9.005 from Meeker
Junction (Seattle Leg)
Connect with Seattle Line at Station 457+83 = Mile 8.675 from Meeker
Junction (Tacoma Leg)
Bihler to Kyle, July 15, 1899
In grading from the connection of the cut-off at Auburn to the Green
River crossing, particular care must be taken in excavating borrow pits
so as not to cause diversion of the water from the rivers. For this
purpoe an ample berm should be left at the river bank and the borrow pit
should not be taken out continuous, but should be rboken at intervals of
not more than 100 feet, by leaving the original ground intact for some
distance. It will also be advisable not to attempt to put up the bank to
the full width, or to full height. Werever matieral is scarce, grade the
banks just wide enoug so that track can be laid. We can get along with
eight feet if necessary, and have the banks graded to a temporary grade
making steep run-offs for the bridges. We will do the widening and
rasing by train. This will make a much more satisfactory job than
putting up the bank to the full cross-seciton and leaving large borrow
pits whic are not only unsightly, but also particularly dangerous in
this locality.
Bihler to Kyle, December 9, 1899
It would seem to me that by this time the resident engineers should have
their cross-section quanities and the scheme of distribution of the
material in such shape that it would not be necessary to take changes
after the work has been starrted and partly carried out. Changes of this
kind after the work is once commenced are always annoying and
undoubtedly add to the expense. The time which has elapsed since
construciton commenced has certainly been sufficent to have all this
preliminary work fully decided, and I wish you would see that the
resident engineers complet the necessary office work as expeditiously as
possible.
Kyle to Bihler, December 12, 1899
I have received your letter of the 9th inst. enclosing letter from
Nelson Bennett which is very characteristic of the man. That is I mean
that he always begins at the wrong place with his objections as well as
his work. I think he should take those things up with the engineer in
charge of the work before going to headquarters and then if he cannot
get satisfaction he has a perfect right to come to headquarters as a
matter of fact there was an error in the distribution of the material at
this point caused by a mistake in the additions in the cut at Sta. 220.
Bennett made an objection when the cut was narrowed and now he objects
to it being widened. There is a distance on each end of the cut of about
20 feet that will not make it more expensive to get but the balance of
the cut is not one bit affected by the change in width. It will probably
effect 700 to 800 yards of material in the cut out of 2,3000 and I have
already made arrangements with Mr. Henry to adjust the matter and there
should have been no trouble in the matter at all as far as Bennett was
concerned. Bennett is noted for ignoring the engineers on the ground and
taking advantage of them by going to headquarters with his troubles. I
do not wish you to take this letter in any other light than I wish to
show up Bennett's unfair ways of dealing with the field engineers.
Kyle to Bihler, January 16, 1900
In response to your wire of today I herewithgive you a report of the
damage done by the recent floods which is not so much.
There was no damage to speak of done to the Palmer Cut-Off till the
2nd crossing is reached. There the water carrieed away the sheet piling
that was in place for the east abutment and pier No. 1 also filing the
excavations up about 1 foot with mud. Pier No. 2 was filled up about 2
feet with mud and the upper end of the coffer dam was stoved in by logs
and the engine that runs the pump was turned over. The west abutment was
not damaged any I think 100 dollars will cover damages at this point.
The embankment along Green River east of Auburn was washed some probably
1,000 yars will cover this. I know of no other damage done.
Ralph Modjeski, Chicago, Ill., to McHenry, February 9, 1900
I enclose herewith a copy of test reports of pin steel for the contracts
with the American Bridge Company. The bridge company have not ordered
their pin steel in the regular manner, but epxcted to use billets
destined for car axles to make pins from as they very often do. I have
tested their car axle material with the results enclosed, ahd have
consequently refusted to accept it.
In connection with this, will you kindly advise me if there is
anything urgent about the bridges under contract with the American
Bridge Company. I anticipate some trouble with the material, having
rejecte a number of steel casting besides this pin material and should
like to know if you would prefer to make some sacrifice as to quality of
matieral in order to get the bridges at as early a date as possible.
[McHenry forwards to Bihler February 12, 1900]
Bihler to McHenry, February 17, 1900
As I wired you, the delivery of these bridges should be made by May 1st.
It would eable us to work to better advianget to have the bridges at an
earlier date, but do not think that we can gain any time in the
completion of the line, and therefore would not recommend that we accept
inferior material.
McHenry to Bihler, March 2, 1900
Kelly-Atkinson Construction Co. say they are advised American Bridge
Works expect to complete shipment Palmer Cut-Off within ten days. They
want to know if everything is ready to erect bridges aslo accomodations
along line for boarding men.
[OK'd by Bihler same date]
Bihler to Kyle, March 2, 1900
Am now advised by the Cheif Engineer that cut-off bridge may be expected
within 10 days. Please cosntruct at once false work for White River and
first crossing Green River and endeavor to have grade completed by the
time White River crossing is erected, so that track can be laid to
second crossing. Push work on masonry on second crossing and send in
your request for cross ties.
Bihler to Kyle, March 14, 1900
Herewith invoices for American Bridge Works for bridges on the Palmer
Cut-Off, as follows:
Feb. 28 -- CM&StP 27747
Feb. 28 -- CM&StP 19839
Feb. 28 -- CM&StP 13999
Feb. 28 -- CM&StP 21089
Feb. 28 -- NP 66035
All of these cars have been forwarded to Palmer. Please have those
cars loaded with mateiral for White River forwarded to Auburn and retunr
invoices with your check.
Bihler to Kyle, March 14, 1900
Please advise what arrangement can be made for sleeping accomodations
for the erecting gang at Palmer. I presume there will be no difficulty
in obtaining suitable accomodations at Auburn and at the Green River
crossing the men can probably sleep in Moyer's camp. Whether there are
any sleeping accomodations to be had at Palmer I do not know. Please
advise as soon as possible, whether bunk cars will have to be provided.
Kyle to Bihler, March 16, 1900
There are no sleeping accomdations at Palmer but they [the bridge
erecting gang] can get board at the section house. We could furnish some
tents to sleep in if you think best.
At Auburn they cn get in at the Green River Hotel and at the 2nd
crossing we can hold our camp there for them. So that we can get along
without bunk cars.
PS-Still I think it would be more agreeabl to the men to give them a
bunk car.
Bihler to Kyle, March 17, 1900
Pearson says he will put in the switch at north leg of wye Auburn
probably Tuseday. Think under circumstances you had beeter put in switch
yourself.
Bihler to Kyle, March 17, 1900
What is reason you cannot lay track faster on Palmer Cut-Off?
Kyle to Bihler, March 17, 1900
Answering yours of the 16 ints. regarding starting steam shove as stated
in my letter of the 15th inst. I would like to get some material in
under the track both on the GR&N Connection and on the aeast end of the
Green River Crossing But of course if you think best I will try and get
along untill the track is lad down to Leary's.
Kyle to Bihler, March 17, 1900
Referring to the progress being made in track laying on the Palmer
Cut-Off they have been laying the track just as fast as the ties arrive.
We are using from 200 to 250 ties per day for dapping which reduces the
amount of track they can lay. I cannot construct consistently ask the
constractors to incrase their force until the ties being to arrive in
sufficient quantities to justify it. I had talked to Mr. Horicks and
McLaughlin 3 weeks before we began to lay track and supposed ties would
arrive in the correct quantities and on time. I cannot see how you can
blame me. If you will look up telegrams & letters you will see that I
have tried to impress everyone that we would start tracklaying about the
5th of March.
Kyle to Bihler, March 19, 1900
Yours of the 14th inst. regarding steam shovel work and track laying
received. I have written Henry and Bennett in regard to hurrying the
track laying to Leary's and hope whty will push the work. As to the
dealy in getting material I will stry and forsee the wants in time to
avodid delay if possible but the delay in the arrival of ties and switch
material is certainly not to be attributed to me as they were ordered 4
or 5 months ago and I have seen and written and I wired a number of
times to your office in regard to there being delivered on time.
Bihler to Kyle, March 20, 1900
It seems that you started on the track laying somewhat too early before
your tie supply was assured. It is of some importance that we get the
track to Leary as soon as possible in order to relieve us of the
necessity of keeping an engine tied up between Henry's and Leary, doing
work for which we receive very little compensation. I should therefere
think that it would be better not to spend any time in laying side
tracks at Palmer, but to push the track laying on the main line towards
Leary. The track laying at Palmer station can be done at any time, and
should not require train service. You should pay some attention to
reducing the cost of the work done in this respect. After tack has been
laid to leary, your work train will be available to handle the gravel
train and the track laying gang can be employed in ballasting, until it
is possible to extend the track further west. It certainly will not pay
to keep a train crew for the purpose of laying 600 or 1,000 feet of
track per day.
It was my understanding that about 4,000 ties had been delivered at
Palmer prioer to the commencement of the track laying, and as you say in
your letter, that about 200 to 250 ties per day of the present reciepts
are used for dapping, I cannot see why you are not using the ties which
you have on hand to make up shortages in your daily reciepts.
Bihler to Kyle, March 21, 1900
Why don't you lay track towards Leary. There is no hurry getting the
track to the Green River crossing from the west.
Kyle to Bihler, March 25, 1900
I understood that ties would begine to arrive promptly on the 5th of
March. I asked your office to have them started so that H&B could start
laying on that date and understood that there would be no trouble in
getting the ties and informed H&B what I had done so that they had a
small gange on the ground but did not actually begin laying until the
8th so that there should not have been any dealy on that account.
I liad about 4,000 fett of track from the stock on hand or until the
10th before any ties began to arrive at all then only or 4 cars per ay.
In regard to laying track at Palmer station it was very necessary to get
the house track laid to be able to handle the cars before starting
toward Leary. But I will admit that we should not have laid it to the
1st crossing or laid the west leg of wye but there was a
misunderstanding of my orders in regard to this. We had to keep the gang
busy and so they put in the switches & west leg of wye at Palmer. The
proper thing to have doen would have been to send the engine & crew back
but I expected ties to be coming along each day and so was greatly lead
on.
PS-I might aslo say that we had about 2,000 ties dapped by the 9th of
the month so that it was impossibel to use the ones dapped and hard to
make up any deficancy. I was anxious to get the dapping and started so
as not to delay the track laying on that account.
Kyle to Bihler, March 29, 1900
H&B have only 40 men laying track and cannot keep the back work up. I
think if they don't get some more men we should put a gang of 8 or 10 on
to fix up track so that the rails will not get surface kinked.
Bihler to Henry & Bennett, March 29, 1900
There are only 40 men in track laying gang. Not enough to keep up back
work. 34 cars ties in Plamer yard which must be released at once.
Bihler to Henry & Bennett, March 29, 1900
The progress of the track laying on the Palmer Cut-Off is extremely
inadequate. Yesterday's report shows only 1,000 feet of track laid, the
reson for the small showing being insufficient force. Apparently your
present force should be doubled to handle the work with anything like
reasonable dispatch. As it is now, the force can only lay for half a
day, because there are no men in the yard to load material on cars to
keep the track laying gang supplied. This not only causes an excessive
amount of engine service, but also makes it necessary to do a great deal
of running over the unballasted track and I wish to avoid this so that
the steel may not get damaged. Please make special effort to get a good
force on this work at once.
Bihler to Henry & Bennett, March 30, 1900
Principal trouble Palmer seems to be inability to retain men account
poor boarding facilities. Not much use to send men out if they won't
stay account poor accomodations. This should be remedied.
Bihler to Kyle, March 29, 1900
As soon as the line below the large cut on Bennett's work is in good
shape for the track to get through, I wish you would arrange to furnish
Mr. Bennett with a train so that he can commence widiening the banks
between Auburn and the Green River crossing. I would like to get this
section of track ballasted as soon as possible so that we can commence
hauling material from the Palmer Cut-Off for the new yard at Auburn, and
possibly also, ballast for ballasting on the Seattle Branch.
H.C. Henry to Bihler, March 30, 1900
The ties will all be unloaded today. Have ordered that quarters for men
are to be made immediately comfortable regardless of cost.
Kyle to Bihler, April 18, 1900
I have decided to run a temporary line around and avoid some of the big
cut on the eastend at Sta. 215. By turning the line down the hill we can
get the track through the cut earlier and by borrowing on the south side
of big fill at 220 we can close that up. Norrow at least, so that it
will not dely the track. There will be some yardage left in the cut
porobably when the fill is completed but by steam shoveling this out and
avoiding the fill in Green River Valley we can gain quite a good deal of
time, fully one month I should think. Does this meet with your approval?
The cut at 565 is dragging slowly and will not be done for about 1 month
so that I do not with the above scheme anticipate any dealy at Sta. 215.
[OK'd by Bihler, April 20, 1900]
Kyle to Bihler, May 31, 1900
I looked over the ground in regard to the ballast on Louisa Nelson's
land today and think it will pay to put a track in and open up a pit. It
will require about 400 lienal feet of rails & fastenings in 2,000 feet
track and I will get Lidell to grading at once if possible. It will aslo
requrie 1,000 ties. I have sent in a req. to cover the material that we
have not on hand.
[OK'd by Bihler June 5, 1900]
Kyle to Bihler, May 31, 1900
33 men laying track and 56 men surgacing please ask Henry to increase
force.
Bihler to Henry & Bennett, May 31, 1900
Reports show you have only 38 men on surfacing and 50 men on track
laying. You promised us an aderquate force on this work, but do not see
that any efforts are being made to fulfill it. You should immediately
increase your tack laying force to 75 men and your surfacing force to at
least 100. Unless this is done by next Monday, I will be compelled to
put on forces of our own.
Bihler to Kyle, June 1, 1900
Have advised Henry that unless sufficient force is put on by next Monday
we will put on our own force surfacing. Advise me each day of the number
of men working on track.
Kyle to Bihler, June 1, 1900
They say that there are plenty of men in Seattle but that they cannot
get them which I consider a very lame excuse. They evidently make no
indeucement for the emn to come or even to keep them after they get them
there in the way of accomodations.
No comments: